Project Timeline

There are five broad stages for the project, as shown below.

Background Review 8 Mar - 24 May 2010
Consultation and Analysis 25 Apr - 1 Oct 2010
Scoping Paper and Feedback 1 Oct - 20 Dec 2010
Draft Strategy and Feedback 1 April - 13 May 2011
Finalise Strategy and Implementation Plan 13 May - to be confirmed

 

Outcomes of each stage of the project will be provided on this site through a series of project updates.  These are available on this project website and through ongoing media releases.   More details about specific consultation activities and how to get involved are also outlined on the project website and will be communicated through regular media releases. We also encourage you to subscribe to the Project and have project updates emailed to you as new details are announced. Click here to join our email list.